E-906/SeaQuest Engineering Notes and Safety Approval
| Apparatus,
System
or Document |
Subsystem |
Subsubsystem |
SeaQuest-DocDB
# (*) |
Projects-doc
# (*) |
Status |
Date
of Submission or Acceptance |
| SeaQuest ORC |
Commissioning
Run |
1499 | Expired | 6-April-2012 |
||
| 2013 Run |
874 |
Approved |
30-October-2013 |
|||
| Safety
Assessment Document (SAD)--from Switchyard 120 |
1439,
1529 |
Approved |
27-January-2012 |
|||
| NEPA |
1226 |
Approved |
21-May-2010 |
|||
| NM4 Hazard
Awareness Training |
1495 | Approved |
5-March-2012 |
|||
| Shielding |
1314 | Approved |
1-March-2012 | |||
| Beam Line
Cherenkov |
Rad Safety |
620 |
Approved |
1-March-2013 |
||
| Electronics |
874 |
Approved |
30-October-2013 |
|||
| Target |
1196, 1505 | Approved by
Cryo Committee |
2-March-2012 |
|||
| Neon Test |
1216 |
Approved |
19-May-2011 |
|||
| Neon Test in NM4 |
1448 |
Approved |
7-February-2012 |
|||
| Target Heater |
1506 | Approved |
14-March-2012 |
|||
| New Target Flasks |
665 |
Approved |
02-April-2013 |
|||
| CryoTarget 2013 Run |
830 |
Approved | 23-August-2013 |
|||
| FMag |
1222,
1147 |
Approved | 26-May-2011 |
|||
| Station 1 |
Cantalever Support |
1205 |
Approved | ?? |
||
| Concrete Wall |
794 |
17-July-2013 |
||||
| X-Hodoscope |
Suspension |
1197, 1228 | Approved | 1-June-2011 |
||
| Unattended Operation Approval |
1235 | Approved | 10-June-2011 | |||
| Y-Hodoscope |
Suspension |
1198, 1228 | Approved | 1-June-2011 | ||
| Unattended Operation Approval | 1235 | Approved | 10-June-2011 | |||
| Old Tracking 866 |
Suspension |
1241,
1476 |
Approved | 20-February-2012 | ||
| Unattended Operation Approval | 1446 |
Approved | 3-Feb-2012 |
|||
| Repair Lifting Eyes |
758 | Approved |
13-June-2013 |
|||
| New Tracking |
Chamber & Electronics |
|||||
| Suspension |
||||||
| KMag |
1222,
1124,
1147 |
Approved | 26-May-2011, 25-Jan-2011 |
|||
| Station 2 |
A-Frame
Structure |
Approved | KTeV approval still valid |
|||
| Fall Protection |
1359 | Approved |
10-November-2011 |
|||
| X-Hodoscope |
Suspension |
1199, 1228 | Approved | 1-June-2011 | ||
| Unattended Operation Approval | 1235 | Approved | 10-June-2011 | |||
| Y-Hodoscope |
Suspension |
1200, 1228 | Approved | 1-June-2011 | ||
| Unattended Operation Approval | 1235 | Approved | 10-June-2011 | |||
| Tracking |
Suspension |
1206 |
Approved | 19-Nov-2009 |
||
| HV Unattended Operation Approval | 1036 |
Approved | 23-Aug-2010 |
|||
| Unattended Operation Approval |
1446 |
Approved | 3-Feb-2012 |
|||
| Station 3 |
I-Beam
Structure |
I-Beam Assembly |
1242 1476 | Approved | 20-February-2012 | |
| Rail system | 1255 1476 | Approved | 20-February-2012 | |||
| Drops | 1243 1476 | Approved | 20-February-2012 | |||
| X-Hodoscopes |
Suspension |
1202 |
Approved | 07-December-2010 | ||
| Unattended Operation Approval | 1235 | Approved | 10-June-2011 | |||
| Plus Tracking |
Suspension |
1201 1476 | Approved | 20-February-2012 | ||
| Unattended Operation Approval | 1446 |
Approved | 3-Feb-2012 |
|||
| Minus 866
Tracking |
Support |
1261 1476 | Approved | 20-February-2012 | ||
| Unattended Operation Approval | 1446 |
Approved | 3-Feb-2012 |
|||
| New Minus
Tracking |
Support |
525 |
Approved |
20 June 2013 |
||
| Iron Wall |
1498 | Approved | 5-March-2012 |
|||
| Station 4 |
X-Hodoscopes |
Suspension | 1203 | Approved | 07-December-2010 |
|
| Unattended Operation Approval | 1235 | Approved | 10-June-2011 | |||
| Y1-Hodoscopes |
Suspension | 1204 | Approved | 07-December-2010 | ||
| Unattended Operation Approval | 1235 | Approved | 10-June-2011 | |||
| Assembly |
1194 | Approved | 07-December-2010 | |||
| Y2-Hodoscopes |
Suspension | 1204 |
Approved | 07-December-2010 | ||
| Unattended Operation Approval | 1235 | Approved | 10-June-2011 |
|||
| Assembly |
1194 | Approved | 07-December-2010 | |||
| Prop. Tubes |
Suspension |
1218 | Expired | 5 March-2012 |
||
| Revised
Suspension |
849 |
old, obsolete note 1218 | Approved |
1-October-2013 |
||
| Low Voltage Supply |
5297 |
1415 |
Approved | 3-Feb-2012 |
||
| Electronics |
5300 |
1416 |
Approved | 3-Feb-2012 |
||
| Unattended Operation Approval | 1446 |
Approved | 3-Feb-2012 |
|||
| 80/20 Load Tests |
753 | Approved |
1-October-2013 | |||
| DAQ &
Electronics |
Latch & TDC Cards |
1207 |
Approved | 25-Aug-2010 |
||
| ASDQ Cards |
780, 1244, 1446 | Approved | 3-Feb-2012 |
|||
| Level Shifter Boards |
780, 1244, 1446 | Approved | 3-Feb-2012 |
|||
| New PMT Bases |
788 | Approved |
22-August-2013 |
|||
| Cabling and setup |
Commissioning Run |
1446 |
Expired | 3-Feb-2012 |
||
| 2013 Run |
874 |
Approved |
30-October-2013 |
|||
| Color
Key |
Needed for 2013 Run
and not yet submitted or approved |
|||||
| New note for
2013 run submitted for approval |
||||||
| Not Installed
for October 2013 |
||||||
| New note for 2013 run approved | ||||||
| Old
system with no changes from Commissioning run |
||||||
* Starting in 2013, SeaQuest switched to SeaQuest-DocDB.fnal.gov. Older documents are on the projects-docdb.fnal.gov.
Paul E. Reimer [email protected] 1 November 2013